Uinta River Trail Resurfacing Project
A portion of the Uinta River Trail would be resurfaced with mineral soil from an adjacent borrow site to improve footing for pack stock.
Project Summary
Current Status:
Completed
Location Summary:
The trail segment is located approximately 1.1 miles from the Uinta Trailhead off Forest Service Road 118, about 2.5 miles south of the High Uintas Wilderness boundary.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/30/2021 |
| Decision | 07/2021 (Estimated) |
| Implementation | 07/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Roosevelt Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Project Decision Information
Uinta River Trail Resurfacing Project
Decision Signed Date: 07/20/2021
Forests:
Ashley National Forest
Districts:
Roosevelt Ranger District
States:
Utah
Counties:
Duchesne
Legal Land Description:
Legal Location of Borrow Pit Site: SE 1/4 NW 1/4, Sec. 19, T3N R2W; Legal Location of North and South Terminus of Trail Segments: SE 1/4 NE 1/4, Sec. 24, T3N R3W; SE 1/4 NW 1/4, Sec.19 T3N R2W.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Stephen Larrabee
650 W. Highway 40
Roosevelt, UT 84066
435-781-5114
stephen.larrabee@usda.gov
Last Updated: 9/30/2021