Avalon Energy Corporation 2D Seismic Exploration
Avalon is proposing to conduct approximately 12.75 miles of 2D seismic exploration during late summer of 2006. Recording sensors and shotholes would be placed along the seismic lines. Shotholes would be drilled and shot.
Project Summary
Location Summary:
In the Strawberry Peak and Shotgun Draw area of the South Unit of the Ashley National Forest,
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/16/2006 |
Comment Period | 05/16/2006 |
Decision | 01/2007 (Estimated) |
Implementation | 06/2007 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Duchesne Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Avalon 2007 Seismic Project
Decision Signed Date: 01/04/2007
Decision Memo Avalon 2007 Seismic Project
Decision Signed Date: 01/04/2007
Legal Notice Date: 01/04/2007
Forests:
Ashley National Forest
Districts:
Roosevelt Ranger District; Duchesne Ranger District
States:
Utah
Counties:
Duchesne
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Herron
85 West Main
Duchesne, Ut 84021
435-781-5218
daherron@fs.fed.us
Last Updated: 3/20/2007