Iron King Mining Project
Proposal to conduct exploratory drilling for locatable minerals on the existing Iron King mining claims within the Farm Creek drainage of the Ashley National Forest.
Project Summary
Location Summary:
Farm Creek
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/14/2008 |
Comment Period | 12/05/2009 |
Decision | 06/2010 (Estimated) |
Implementation | 07/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Duchesne Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Iron King Drilling Proposal
Decision Signed Date: 06/22/2010
Legal Notice Date: 06/22/2010
Forests:
Ashley National Forest
Districts:
Roosevelt Ranger District
States:
Utah
Counties:
Duchesne
Legal Land Description:
Section 29 of T3N R1W, Uinta Special Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Herron
85 West Main
Duchesne, Ut 84021
435-781-5218
daherron@fs.fed.us
Last Updated: 2/24/2011