Greendale Water Company Facility Upgrade Project
Modify existing permit to all for the construction a new water treatment plant, install a new partially buried water tank and construct a 700 square yard gravel parking area within the existing site boundary.
Project Summary
Location Summary:
Located in Section 29, T2N, R22E, SLM, Daggett County, Utah.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/03/2014 |
Decision | 12/2014 (Estimated) |
Implementation | 12/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Flaming Gorge Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Greendale Water Company Amendment
Decision Signed Date: 12/01/2014
Forests:
Ashley National Forest
Districts:
Flaming Gorge Ranger District
States:
Utah
Counties:
Daggett
Legal Land Description:
Located in Section 29, T2N, R22E, SLM, Daggett County, Utah.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jayson Roundy
25 West Highway 43
Manila, UT 84046
435-781-5281
jcroundy@fs.fed.us
Last Updated: 12/4/2014