South Fork Rock Creek Headcut Stabilization
The Forest proposes actions to stabilize a gully and cutbank bordering the floodplain of the South Fork Rock Creek. Stabilization efforts will alleviate erosion that is delivering sediment to the South Fork of Rock Creek and its surrounding wetland.
Project Summary
Location Summary:
Adjacent to the S Fk Rock Creek, near the confluence with Rock Creek, 1 mi below Upper Stillwater Dam, 31 mi NW of Duchesne, UT.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/10/2014 |
Decision | 09/2014 (Estimated) |
Implementation | 10/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (19), 36 Cfr 220.6(E)(19)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ashley National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management; Watershed Management
Project Activity:
Special Area Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
South Fork Rock Creek Headcut Stabilization
Decision Signed Date: 09/17/2014
Forests:
Ashley National Forest
Districts:
Duchesne Ranger District
States:
Utah
Counties:
Duchesne
Legal Land Description:
SW Sec 21, T2N, R7W, Uintah Base Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Plunkett
355 North Vernal Ave
Vernal, UT 84078
435-781-5140
cplunkett@fs.fed.us
Last Updated: 2/27/2015