Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/11/2017 |
Comment Period | 07/25/2017 |
Objection Period Start | 09/12/2017 |
Decision | 11/2017 (Estimated) |
Implementation | 11/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Nepa Document Prepared By Another Federal Agency; Ira - Inventoried Roadless Area Activities Requiring Chief's Approval
Lead Management Unit:
Ashley National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Natural Gas; Oil
Current Status:
Completed
Project Decision Information
Berry Petroleum Lease Reinstatement Project - UTU77328
Decision Signed Date: 11/03/2017
Forests:
Ashley National Forest
Districts:
Duchesne Ranger District
States:
Utah
Counties:
Duchesne
Legal Land Description:
T6S, R5W, Sections 7, 8, and 18.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Scott Bingham
355 North Vernal Ave
Vernal, UT 84078
435-781-5107
srbingham@fs.fed.us
Last Updated: 11/3/2017