Lowline Trail New Construction
Approximately 0.5 miles of new non-motorized trail construction to replace a section of the current Lowline Trail.
Project Summary
Location Summary:
The trail construction would occur adjacent to the Lowline Trailhead parking lot near the Cedar Springs sewer lagoons in the Flaming Gorge National Recreation Area (NRA).
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/25/2024 |
Decision | 06/2024 (Estimated) |
Implementation | 08/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Flaming Gorge Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Lowline Trail New Construction
Decision Signed Date: 06/21/2024
Forests:
Ashley National Forest
Districts:
Flaming Gorge Ranger District
States:
Utah
Counties:
Daggett
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kevin Clegg
25 West Highway 43
Manila, UT 84046
435-784-3445
kevin.clegg@usda.gov
Last Updated: 6/24/2024