Bowery Creek Road Reconstruction and Easement
Resurfacing and some reconstruction of 6.0 miles of paved (3.8 miles) and gravel (2.2 miles) road on National Forest System road. Replacement of one bridge. Issuance of easement for road to Iron County.
Project Summary
Location Summary:
Approximately 4 miles southeast of Parowan, Utah.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/24/2010 |
| Comment Period | 09/28/2010 |
| Decision | 01/2011 (Estimated) |
| Implementation | 05/2011 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cedar City Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Road Management; Watershed Management
Project Activity:
Special Use Authorizations; Road Improvements/Construction; Watershed Improvements
Current Status:
Completed
Project Decision Information
Bowery Creek Road Reconstruction and Easement
Decision Signed Date: 01/10/2011
Legal Notice Date: 01/12/2011
Forests:
Dixie National Forest
Districts:
Cedar City Ranger District
States:
Utah
Counties:
Iron
Legal Land Description:
T34N, R8W, Sec 31. T35S, R8W, Sec 6,7,8,9,16,17,20.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dave Swank
1789 North Wedgewood Lane
Cedar City, UT 84721-7769
435-865-3224
dswank@fs.fed.us
Last Updated: 9/24/2012