Arcadian Broadband Fiber Optic
The Dixie National Forest is analyzing a proposal from Arcadian Infracom, Inc. (Arcadian), for the installation of a fiber optic cable (communication line) and related facilities on approximately 683 linear feet of National Forest System Lands.
Project Summary
Location Summary:
This project proposes to place a communication line, and related structures within a new 10-foot wide (.16 acre) right-of-way (ROW) from Orderville to Bear Valley, contained within the Highway 89 corridor
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/04/2021 |
Decision | 08/2023 (Estimated) |
Implementation | 07/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Dixie National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Arcadian Broadband Fiber Optic
Decision Signed Date: 08/30/2023
Forests:
Dixie National Forest
Districts:
Cedar City Ranger District
States:
Utah
Counties:
Kane
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Michael Golden
820 N. Main Street
Cedar City, UT 84721
435-865-3726
michael.golden@usda.gov
Last Updated: 8/30/2023