Dixie Power
These lines provide electrical service to businesses, residences, Washington County and Forest Service facilities. Re-issue and response to the application from Dixie Power would allow for the continuation of service.
Project Summary
Location Summary:
Pine Valley to Pinto, Pinto to New Castle, Pine Valley Campground%u200B
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/13/2023 |
Decision | 11/2023 (Estimated) |
Implementation | 11/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3); 32.12 (11), 36 Cfr 220.6(D)(11)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pine Valley Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Dixie Power
Decision Signed Date: 11/01/2023
Forests:
Dixie National Forest
Districts:
Pine Valley Ranger District
States:
Utah
Counties:
Washington
Legal Land Description:
Section 30 T 38 S R 14 W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kathy Slack
196 E. Tabernacle, Suite 40
St. George, UT 84770
435-865-3742
kathleen.slack@usda.gov
Last Updated: 11/1/2023