Cross-Tie 500-kV Transmission Project
Construction, operation, maintenance and decommissioning of a 500kV transmission line between Clover Substation in Juab County, Utah, and Robinson Summit Substation in White Pine County,Nevada
Project Summary
Location Summary:
The Project is located in Beaver, Juab, and Millard Counties, Utah, and White Pine County, Nevada.
Project Milestones:
Milestone | Date |
---|---|
NOI in Federal Register | 05/02/2022 |
DEIS NOA in Federal Register | 11/09/2023 |
FEIS NOA in Federal Register | 09/20/2024 |
Objection Period Start | 09/21/2024 |
Decision | 09/2025 (Estimated) |
Implementation | 09/2025 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ely Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
In Progress
Forests:
Humboldt-Toiyabe National Forest
Districts:
Ely Ranger District
States:
Nevada
Counties:
White Pine
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marnie Bonesteel
825 Avenue East
Ely, NV 89301
775-352-1240
marnie.bonesteel@usda.gov
Last Updated: 3/14/2025