Rock Creek Stream Restoration Project
Rock Creek Road, FSR 12N70, was heavily impacted by the Winter storms of 2022 and is currently impassable. The existing culvert will be replaced with a newly designed culvert and the road and slope will be stabilized.
Project Summary
Location Summary:
Washout located on Rock Creek Road, FSR 12N70
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/11/2024 |
| Decision | 09/2024 (Estimated) |
| Implementation | 09/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Georgetown Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Road Management
Project Activity:
Road Maintenance; Road Improvements/Construction; Watershed Improvements
Current Status:
Completed
Project Decision Information
Rock Creek Stream Restoration Project
Decision Signed Date: 09/19/2024
Forests:
Eldorado National Forest
Districts:
Georgetown Ranger District
States:
California
Counties:
El Dorado
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Colleen Sloan
7600 Wentworth Springs Rd
Georgetown, CA 95634
209-259-3447
colleen.sloan@usda.gov
Last Updated: 9/19/2024