BNF Rush Creek/NFSR 263 Culvert Replacement Project
The existing culvert will be replaced with a single span bridge, with abutment walls and wingwalls designed to pass a 50-year flood event and span the bankfull width of Rush Creek.
Project Summary
Current Status:
Completed
Location Summary:
6th level HUC: Rush Creek-Brushy Creek(031601100201)
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/23/2013 |
| Comment Period | 08/17/2013 |
| Objection Period Start | 10/31/2013 |
| Decision | 11/2014 (Estimated) |
| Implementation | 02/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bankhead Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Wildlife, Fish, Rare Plants; Road Management
Project Activity:
Species Habitat Improvements; Road Improvements/Construction
Project Decision Information
Rush Creek Culvert Replacement Project
Decision Signed Date: 11/20/2014
Forests:
National Forests in Alabama
Districts:
Bankhead Ranger District
States:
Alabama
Counties:
Winston
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Erika Davis
P.O. Box 278
Double Springs, AL 35553
334-241-8108
erikadavis@fs.fed.us
Last Updated: 11/20/2014