Alabama Power Company Muscadine 115kV Transmission Line
New 115kV Transmission Line right-of-way
Project Summary
Current Status:
Completed
Location Summary:
SEC 19, TWN 15S, RNG 11E
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/10/2013 |
| Comment Period | 03/10/2013 |
| Decision | 08/2013 (Estimated) |
| Implementation | 09/2013 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Shoal Creek Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Alabama Power Company 2013 Muscadine 115kV TL Transmission Line Right-of-Way Special Use Permit
Decision Signed Date: 08/05/2013
Legal Notice Date: 08/05/2013
Forests:
National Forests in Alabama
Districts:
Shoal Creek Ranger District
States:
Alabama
Counties:
Cleburne
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mary Humphries
45 Highway 281
Heflin, AL 36264
256-362-2909 x 145
mhumphries@fs.fed.us
Last Updated: 9/30/2013