Central Alabama Electric Cooperative, Chilton and Perry Fiber System
Special Use application for overhead fiber optic line install and maintenance of existing infrastructure.
Project Summary
Location Summary:
Within approximately 5 mile radius of the Chilton and Perry county line along Hwy 183.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/24/2021 |
Decision | 04/2021 (Estimated) |
Implementation | 05/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Oakmulgee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Cancelled
Forests:
National Forests in Alabama
Districts:
Oakmulgee Ranger District
States:
Alabama
Counties:
Chilton; Perry
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dustin Beaty
9901 Highway 5
Brent, AL 35034-3801
205-926-9765
dustin.l.beaty@usda.gov