2024 FSR 512 Road Powerline Special Use
Special Use proposal to install an aerial power supply line to private property
Project Summary
Current Status:
Completed
Location Summary:
T18S R9E Sec 18 Along USFS Road 512 on the Shoal Creek Ranger District.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/19/2024 |
| Decision | 04/2025 (Estimated) |
| Implementation | 04/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Shoal Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
2024 FSR 512 Road Powerline Special Use
Decision Signed Date: 04/29/2025
Forests:
National Forests in Alabama
Districts:
Shoal Creek Ranger District
States:
Alabama
Counties:
Clay
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gregory Scull
45 Highway 281
Heflin, AL 36264
256-463-2273
gregory.l.scull@usda.gov
Last Updated: 4/30/2025