Brushy Creek Bridge Replacement
Brushy Creek Bridge Replacement
Project Summary
Location Summary:
Brushy Creek Bridge
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/15/2008 |
| Comment Period | 11/14/2009 |
| Decision | 01/2010 (Estimated) |
| Implementation | 02/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bankhead Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Road Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Brushy Creek Bridge Replacement
Decision Signed Date: 01/25/2010
Legal Notice Date: 01/30/2010
Forests:
National Forests in Alabama
Districts:
Bankhead Ranger District
States:
Alabama
Counties:
Lawrence; Winston
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Enid Erickson
P.O. Box 278
Double Springs, AL 35553
205-489-5111
eerickson@fs.fed.us
Last Updated: 6/30/2010