Perry County Road 51 Widening Project
The proposed action would widen two sections of Perry County RD 51 that currently pose safety and environmental concerns. The sections total approximately 0.4 mles in Compartments 113 and 118.
Project Summary
Location Summary:
Talladega NF, Oakmulgee RD, Compartments 113 and 118, Perry County Road 51
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/14/2011 |
| Decision | 11/2011 (Estimated) |
| Implementation | 11/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Oakmulgee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Current Status:
Completed
Project Decision Information
Perry County Road 51 Widening Project
Decision Signed Date: 11/28/2011
Forests:
National Forests in Alabama
Districts:
Oakmulgee Ranger District
States:
Alabama
Counties:
Perry
Legal Land Description:
Section 4; T21N; R9E; Perry County, AL
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Joseph Koloski
9901 Highway 5
Brent, AL 35034-3801
205-926-9765
jkoloski@fs.fed.us
Last Updated: 11/29/2011