BKNF Hemlock Woolly Adelgid Suppression
Integrated treatments in a effort to retain a portion of the hemlock on the Bankhead National Forest.
Project Summary
Location Summary:
Bankhead National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/07/2012 |
| Comment Period | 09/01/2012 |
| Decision | 09/2013 (Estimated) |
| Implementation | 09/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
National Forests in Alabama All Units
Notice and Comment Regulation:
215
Project Purpose:
Research; Wildlife, Fish, Rare Plants; Vegetation Management (Other Than Forest Products); Watershed Management; Fuels Management
Project Activity:
Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Scenery Management; Wilderness Management
Current Status:
Completed
Project Decision Information
BKNF Hemlock Woolly Adelgid Suppression
Decision Signed Date: 06/27/2013
Legal Notice Date: 09/21/2013
BKNF Hemlock Woolly Adelgid Suppression(Sipsey)
Decision Signed Date: 09/27/2013
Forests:
National Forests in Alabama
Districts:
Bankhead Ranger District
States:
Alabama
Counties:
Franklin; Lawrence; Winston
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Eugene Brooks
2946 Chestnut St.
Montgomery, AL 36107-3010
334-241-8149
ebrooks01@fs.fed.us