Tallaseehatchee Bridge
Construction of new bridge to replace a 75 year old multi-span bride.
Project Summary
Location Summary:
Located at the Tallaseehatchee Creek crossing on FSR 607
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/03/2014 |
| Comment Period | 02/12/2014 |
| Decision | 06/2017 (Estimated) |
| Implementation | 07/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Talladega Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Watershed Management; Road Management
Project Activity:
Road Improvements/Construction; Watershed Improvements
Current Status:
Completed
Project Decision Information
Tallaseehatchee Bridge
Decision Signed Date: 06/21/2017
Forests:
National Forests in Alabama
Districts:
Talladega Ranger District
States:
Alabama
Counties:
Clay
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Art Henderson
1001 North Street (Hwy 21 North)
Talladaga, AL 35160
256-362-2909
arthenderson@fs.fed.us
Last Updated: 7/18/2017