Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/12/2017 |
| Decision | 07/2017 (Estimated) |
| Implementation | 08/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Talladega Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Land Ownership Management; Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Gaston Yellow Dirt Powerline Additional Space
Decision Signed Date: 07/17/2017
Forests:
National Forests in Alabama
Districts:
Talladega Ranger District
States:
Alabama
Counties:
Clay
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gloria Nielsen
1001 North Street (Hwy 21 North)
Talladaga, AL 35160
256-362-2909 x121
glorianielsen@fs.fed.us
Last Updated: 12/10/2019