Longleaf Restoration - Phase II
The Longleaf Restoration EIS (1999) documents the need for a 30-year program to complete conversion of off-site species to restore the native longleaf ecosystem and proposed the first 5-year plan of action. This project continues this work.
Project Summary
Location Summary:
Conecuh National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/17/2009 |
| Comment Period | 12/17/2009 |
| Decision | 06/2010 (Estimated) |
| Implementation | 09/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Conecuh Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants; Vegetation Management (Other Than Forest Products); Forest Products
Project Activity:
Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Longleaf Ecosystem Restoraton II Project
Decision Signed Date: 06/28/2010
Legal Notice Date: 06/29/2010
Forests:
National Forests in Alabama
Districts:
Conecuh Ranger District
States:
Alabama
Counties:
Covington; Escambia
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Deborah Foley
24481 AL HIGHWAY 55
Andalusia, AL 36420
334-222-2555
dfoley@fs.fed.us
Last Updated: 6/30/2010