Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/07/2025 |
| Comment Period | 02/07/2025 |
| Decision | 03/2025 (Estimated) |
| Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bankhead Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Forest Service Road 263 Waterline Special Use Permit
Decision Signed Date: 03/12/2025
Forests:
National Forests in Alabama
Districts:
Bankhead Ranger District
States:
Alabama
Counties:
Lawrence
Legal Land Description:
Township 8 South, Range 6 West, Section 19, Lawrence County, AL
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tyler Fish
P.O. Box 278
Double Springs, AL 35553
205-973-1845
tyler.fish@usda.gov
Last Updated: 3/13/2025