Anderson Creek ORV Trail System Reroute and Construction
Anderson Creek ORV Trail System Reroute and Construction.
Project Summary
Location Summary:
Gilmer County, GA
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/15/2004 |
Decision | 10/2004 (Estimated) |
Implementation | 11/2004 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Blueridge Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Anderson Creek ORV Trail System Reroute and Construction
Decision Signed Date: 10/28/2004
Forests:
Chattahoochee-Oconee National Forests
Districts:
Blueridge Ranger District
States:
Georgia
Counties:
Gilmer
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Joni Wheeler
1881 Highway 515
Blairsville, GA 30514
770-297-3063
jwheeler@fs.fed.us
Last Updated: 12/29/2016