Upper Warwoman Vegetation Management
The conditions in the Upper Warwoman Project Area indicate a need to restore and maintain shortleaf pine/table mountain pine/pitch pine and Dry Mesic Oak woodland communities, maintain and regenerate oak and oak-pine forests, and improve W/L habitat
Project Summary
Location Summary:
Rabun County, GA
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/07/2013 |
Comment Period | 01/28/2013 |
Objection Period Start | 06/18/2015 |
Decision | 10/2015 (Estimated) |
Implementation | 02/2016 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chattooga River Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements
Current Status:
Completed
Project Decision Information
Upper Warwoman Vegetation Management.
Decision Signed Date: 10/31/2015
Forests:
Chattahoochee-Oconee National Forests
Districts:
Chattooga River Ranger District
States:
Georgia
Counties:
Rabun
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mike Brod
809 Highway 441S
Clayton, GA 30525
706-754-6221
mbrod@fs.fed.us
Last Updated: 9/21/2019