Hartford Wastewater Testing Project
Prepare a study for determination of an area with adequate suitability for beneficial re-use of treated wastewater.
Project Summary
Location Summary:
Cocke County, TN
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/04/2017 |
Decision | 12/2017 (Estimated) |
Implementation | 01/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Unaka Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Research
Project Activity:
Research And Development
Current Status:
Cancelled
Forests:
Cherokee National Forest
Districts:
Unaka Ranger District
States:
Tennessee
Counties:
Cocke
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jonathan Lampley
4900 Asheville Hwy.
Greenville, TN 37743
404-347-5264
jlampley@fs.fed.us
Last Updated: 7/27/2021