Upper Passage Stream Habitat Enhancement
Restore a segment of Upper Passage Creek by placement of large woody debris, rock vanes and weirs, modifying vehicle access, and improving stream bank stability and trail integrity at Lion's Tale Trail area.
Project Summary
Current Status:
Completed
Location Summary:
Upper Passage Creek in the Crisman Hollow Area, Page County
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/20/2015 |
| Decision | 08/2015 (Estimated) |
| Implementation | 09/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
George Washington and Jefferson National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Watershed Improvements
Project Decision Information
Upper Passage Creek Stream Restoration
Decision Signed Date: 08/07/2015
Forests:
George Washington and Jefferson National Forest
Districts:
Lee Ranger District
States:
Virginia
Counties:
Page
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dawn Kirk
5162 Valleypointe Parkway
Roanoke, VA 24019
540-291-5211
dkirk@fs.fed.us
Last Updated: 8/14/2015