Virginia Coal Field Coalition Fiberoptic Cable
VCC plans to install fiberoptic cable across National Forest land on the Clinch Ranger District. Three different segments of cable are planned and will be placed in existing utiltiy corridors.
Project Summary
Location Summary:
Segment 1 - Eagle Knob to Norton, 2 - 4017 ' along Rt. 72 north of Jaybird Branch Rd., 3 - 4115' along Rt. 72 between Retford and Mosswood.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/01/2013 |
Comment Period | 04/05/2013 |
Decision | 05/2013 (Estimated) |
Implementation | 06/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Clinch Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Virginia Coalfield Coalition Fiberoptic Cable Project
Decision Signed Date: 05/30/2013
Forests:
George Washington and Jefferson National Forest
Districts:
Clinch Ranger District
States:
Virginia
Counties:
Wise
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Skinner
1700 Park Ave SW
Norton, VA 24273
276-328-2931
dlskinner@fs.fed.us
Last Updated: 6/26/2013