Mills Creek Yellow Pine Restoration Project
Prescribed burn in conjunction with mechanical treatments on order to promote the regeneration of Southern Yellow Pine species (such as Pitch Pine and Short-leaf Pine) within a 1,179 acre project area.
Project Summary
Location Summary:
Project Area is located north of Sherando Recreation Area and south of the Coal Road (FSR 42).
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/07/2014 |
Decision | 06/2014 (Estimated) |
Implementation | 11/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (5), 36 Cfr 220.6(E)(5)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Glenwood and Pedlar Ranger Districts
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements
Current Status:
Completed
Project Decision Information
Mill Creek Yellow Pine Restoration Project
Decision Signed Date: 06/09/2014
Forests:
George Washington and Jefferson National Forest
Districts:
Glenwood and Pedlar Ranger Districts
States:
Virginia
Counties:
Augusta
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Daniel Wright
27 Ranger Lane
Natural Bridge Station, VA 24579
540-291-2188
djwright@fs.fed.us