Mt. Storm to Valley 500kV Electric Transmission Line Replacement
The line proposed for replacement runs for about 64.5 miles from Dominion's existing Mt. Storm substation in Grant County, W.VA to the existing Valley substation in Augusta, of which 15.5 miles crosses the George Washington National Forest.
Project Summary
Location Summary:
The line runs for about 64.5 miles from Dominion%u2019s existing Mt. Storm substation in Grant County, W.VA to the existing Valley substation in Augusta County, VA.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/02/2020 |
Decision | 11/2021 (Estimated) |
Implementation | 12/2021 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
North River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Mt. Storm to Valley 500kV Electric Transmission Line Replacement
Decision Signed Date: 11/03/2021
Forests:
George Washington and Jefferson National Forest
Districts:
North River Ranger District
States:
Virginia; West Virginia
Counties:
Rockingham; Pendleton
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public