Grayson County Fiber Optic Install - Volney to Fairwood Section
Appalachian Electric Power will install new fiber-optic cable in the existing 40-foot wide right-of-way. Total length is approximately 1,950 feet, and will use up to eight existing poles.
Project Summary
Location Summary:
Grayson County, Virginia
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/13/2021 |
Decision | 09/2021 (Estimated) |
Implementation | 10/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
George Washington and Jefferson National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Grayson County Fiber Optic Install - Volney to Fairwood Section
Decision Signed Date: 09/28/2021
Forests:
George Washington and Jefferson National Forest
Districts:
Mount Rogers National Recreation Area
States:
Virginia
Counties:
Grayson
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tom Blevins
5162 Valleypointe Parkway
Roanoke, VA 24019
276-783-5196
thomas.blevins@usda.gov