KU/ODP Powerline Rebuild Project
Kentucky Utilities Company d/b/a Old Dominion Power Company (KU/ODP) is proposing to replace 28 69kV electrical transmission line poles within an existing right-of-way across the Jefferson NF in Wise County, VA
Project Summary
Location Summary:
Wise County, Virginia
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/04/2022 |
Decision | 03/2025 (Estimated) |
Implementation | 03/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Clinch Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
KU/ODP Powerline Rebuild Project2022 KU/ODP Powerline Rebuild Project
Decision Signed Date: 03/20/2025
Forests:
George Washington and Jefferson National Forest
Districts:
Clinch Ranger District
States:
Virginia
Counties:
Wise
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tiffany Cummins
1700 Park Ave SW
Norton, VA 24273
435-636-3576
tiffany.cummins@usda.gov
Last Updated: 3/21/2025