Bland County Water System Improvements Project
Federal authorization to cross National Forest land is needed to allow for the construction of an interconnecting waterline that will provide water service to over 400 residential customers in Bland / Rocky Gap and along the Route 42 corridor.
Project Summary
Location Summary:
The project is located between Bastian and Bland, Virginia, west of I-77. Portions of this work will occur on USFS lands on Brushy Mountain in Bland County
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/24/2023 |
Comment Period | 12/06/2023 |
Decision | 03/2024 (Estimated) |
Implementation | 04/2024 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Eastern Divide Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Bland County Water System Improvements Project
Decision Signed Date: 03/04/2024
Forests:
George Washington and Jefferson National Forest
Districts:
Eastern Divide Ranger District
States:
Virginia
Counties:
Bland
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Melissa Robinson
110 Southpark Dr.
Blacksburg, VA 24060
540-432-8232
melissa.robinson1@usda.gov