South Mississippi Electric Power Association (SMEPA) Powerline Reconstruction
SMEPA has requested permission to reconstruct portions of their electric transmission lines across National Forest System lands on the Bienville National Forest in order to upgrade the facilities within their network.
Project Summary
Current Status:
Completed
Location Summary:
Scott County Section 30 of Township 5 North, Range 8 East and Sections 22 and 23 of T 5 N, R 7 E; Smith Cty Sections 5, 9, 22, 27, 34, and 35 of T 4 N, R 8 E and Sections 2 and 11 of T 3 N, R 8 E.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/03/2013 |
| Comment Period | 04/03/2013 |
| Decision | 05/2013 (Estimated) |
| Implementation | 06/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bienville Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
SMEPA Transmission Line Reconstruction
Decision Signed Date: 05/22/2013
Legal Notice Date: 06/21/2013
Forests:
National Forests In Mississippi
Districts:
Bienville Ranger District
States:
Mississippi
Counties:
Scott; Smith
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marc Weathersby
3473 Hwy. 35S
Forest, MS 39074
601-469-3811
maweathersby@fs.fed.us
Last Updated: 6/21/2013