| Milestone | Date |
|---|---|
| Scoping Start | 04/29/2019 |
| Decision | 05/2019 (Estimated) |
| Implementation | 08/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
De Soto Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Project Decision Information
Camp Shelby South Tank Trail Realignment and Maintenance
Decision Signed Date: 05/21/2019
Forests:
National Forests In Mississippi
Districts:
De Soto Ranger District
States:
Mississippi
Counties:
Forrest; Perry
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
James Allen
654 W. Frontage Rd.
Wiggins, MS 39577
601-584-8488
davidallen@fs.fed.us
Last Updated: 6/7/2019