East Mississippi EPA Aerial Fiber Project
The Tombigbee Ranger District proposes to issue a special use authorization for installation of 12.6 mi. of fiber optic cable on existing electrical transmission line utility poles in Winston Co., MS
Project Summary
Current Status:
Completed
Location Summary:
The project area occurs in Winston Co., along existing powerlines, within approximately 12 miles northeast of Louisville, MS.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/25/2023 |
| Decision | 06/2023 (Estimated) |
| Implementation | 06/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tombigbee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
East Mississippi EPA Aerial Fiber Project
Decision Signed Date: 06/06/2023
Forests:
National Forests In Mississippi
Districts:
Tombigbee Ranger District
States:
Mississippi
Counties:
Winston
Legal Land Description:
T15N R12E Sec 3; T16N R12E Sec 21-22, 27, 33-35; T16N R13E Sec 2-3, 5-6, 20-24, 26-28, 32, 35; and T16N R14E Sec 3, 8-10, 16-19, 21, 28, 33.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Austin Byrd
6052 MS Hwy 15
Ackerman, MS 39735
662-285-3264
Austin.Byrd@usda.gov
Last Updated: 7/13/2023