Camp Shelby Wetland Crossing Construction
The construction of 31 wetland crossings within the confines of Training Areas 10, 25, 32, and 33 at Camp Shelby Joint Forces Training Center within the De Soto National Forest.
Project Summary
Location Summary:
Perry County Mississippi
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/29/2019 |
Comment Period | 08/19/2019 |
Objection Period Start | 10/01/2019 |
Decision | 11/2019 (Estimated) |
Implementation | 12/2019 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
De Soto Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Harzardous Waste Compliance Actions
Current Status:
Completed
Project Decision Information
Camp Shelby Wetland Crossing Construction
Decision Signed Date: 11/15/2019
Forests:
National Forests In Mississippi
Districts:
De Soto Ranger District
States:
Mississippi
Counties:
Perry
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
James Allen
654 W. Frontage Rd.
Wiggins, MS 39577
601-584-8488
james.d.allen@usda.gov
Last Updated: 1/19/2021