SWMS Electric Installation on FSR 186B
Installation of an electric powerline along right-of-way of FSR 186B for approx. 350' overhead and 3,150' of underground line.
Project Summary
Location Summary:
In the right-of-way of FSR 186B from Pothook Road to private property, approximately 3,400 feet. Line will be underground except where it needs to cross a creek.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/26/2019 |
Decision | 01/2022 (Estimated) |
Implementation | 01/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Homochitto Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Area Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
SWMS Electric Installation on FSR 186B
Decision Signed Date: 01/10/2022
Forests:
National Forests In Mississippi
Districts:
Homochitto Ranger District
States:
Mississippi
Counties:
Franklin
Legal Land Description:
T5N, R3E, Section 9; T6N, R3E, section 38
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Michael Everett
Route 1, Box 1
Meadville, MS 39653
601-384-5876
meverett@fs.fed.us
Last Updated: 1/12/2022