Peasley Creek Road Project
The proposed action for this project is to stabilize the road and return it to safe travel standards by installing mechanically stabilized earth (MSE) geotextile walls, or geotextile reinforced fill, in approximately 20 areas where road shoulder fill slopes have failed or have some probability of future failure, and to reduce road related effects to the Peasley Creek drainage.
Project Summary
Current Status:
Completed
Location Summary:
Clearwater Ranger District
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/27/2009 |
| Comment Period | 07/12/2010 |
| Decision | 08/2010 (Estimated) |
| Implementation | 10/2011 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Clearwater Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Road Management; Watershed Management
Project Activity:
Road Improvements/Construction; Watershed Improvements
Project Decision Information
Peasley Creek Road Project
Decision Signed Date: 08/20/2010
Legal Notice Date: 08/27/2010
Forests:
Nez Perce-Clearwater National Forest
Districts:
Clearwater Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
T29N, R5E, Sections 11, 14, 23, 26, and 29
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Harper
104 Airport Road
Grangeville, ID 83530
208-983-4021
dharper@fs.fed.us
Last Updated: 4/25/2011