Race Creek Culverts
Removal of two undersized culverts and replacement as follows: Site 1: 103" span x 71" rise corrugated steel pipe-arch with a 46' length; and, Site 2: a concrete box culvert, currently being designed.
Project Summary
Current Status:
Completed
Location Summary:
Site 1: MP 19.5 Selway Road; Site 2: Approximately 100 feet upstream from that location in an exisitng campsite.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/25/2014 |
| Decision | 04/2015 (Estimated) |
| Implementation | 05/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Moose Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
Decision Memo
Decision Signed Date: 04/21/2015
Forests:
Nez Perce-Clearwater National Forest
Districts:
Moose Creek Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
NE 1/4 T31N, R9E, Section 12 (Boise Meridian)
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lynelle Knehans
831 Selway Road
Kooskia, ID 83539
208-476-8260
lmknehans@fs.fed.us
Last Updated: 4/22/2015