South Fork #I, II, III Exploration Project
The purpose of the proposed action is to test for gold values on unpatented mining claims. The need is to determine if sufficient quantities of valuable minerals exist to warrant further exploration or development.
Project Summary
Current Status:
Completed
Location Summary:
Access to the claims will be the paved French Mountain Road #250 and unpaved NFS Roads #542, #5120 and #5173, as well as a number of logging roads and trails.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/01/2015 |
| Decision | 07/2016 (Estimated) |
| Implementation | 08/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
North Fork Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
South Fork #I, II, III Exploration Project
Decision Signed Date: 07/27/2016
Forests:
Nez Perce-Clearwater National Forest
Districts:
North Fork Ranger District
States:
Idaho
Counties:
Clearwater
Legal Land Description:
T36N R6E, Sec. 3, 10, 11, 14, 15, 16
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rebecca Anderson
12730B Highway 12
Orofino, ID 83544
208-476-8351
rebeccaanderson@fs.fed.us
Last Updated: 8/3/2016