Hazard Tree Removal
Several decades of accumulated MPB mortality and disease have created serious fuels and public safety concerns. Roads identified for treatment are major arterials are major arterials in the event of emergency or natural disaster.
Project Summary
Location Summary:
Various - please see map in Scoping letter
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/01/2015 |
Decision | 03/2016 (Estimated) |
Implementation | 04/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (14), 36 Cfr 220.6(E)(14)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Vegetation Management (Other Than Forest Products); Road Management; Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance
Current Status:
Cancelled
Forests:
Nez Perce-Clearwater National Forest
Districts:
Red River Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
Various - please see map in Scoping letter
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Edward Koberstein
300 American River Road
Elk City, ID 83525
406-295-7456
ekoberstein@fs.fed.us