Five Mile ATV Bridge Replacement
Replace existing timber bridge with steel stringer bridge. Reconstruct 100 ft. of NF Trail 821 surrounding site to align bridge approaches. Rehab and close unauthorized ford using local native vegetation. To be started in 2017 or 2018.
Project Summary
Current Status:
Completed
Location Summary:
Township 28 North, Range 7 East, Section 36; County 233 road (milepost 10.5); Idaho County, Idaho
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/28/2017 |
| Decision | 06/2017 (Estimated) |
| Implementation | 07/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Wildlife, Fish, Rare Plants
Project Activity:
Trail Management
Project Decision Information
Five Mile ATV Bridge Replacement
Decision Signed Date: 06/08/2017
Forests:
Nez Perce-Clearwater National Forest
Districts:
Red River Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Anne Connor
300 American River Road
Elk City, ID 83525
208-476-4541
aconnor@fs.fed.us