Stove Draw Fence Relocation
The Stove Draw fence crosses a very boggy draw with seasonal water flow. The permittees propose to remove 1500 ft. of existing fence and rebuild 2200 ft. of new fence along a dry ridgeline to the east. Work would take one to two weeks to complete.
Project Summary
Current Status:
Completed
Location Summary:
T41N, R1W, Section 10, Latah County, Idaho
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/10/2017 |
| Decision | 10/2017 (Estimated) |
| Implementation | 05/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Palouse Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management
Project Activity:
Grazing Allotment Management; Grazing Structural Improvements
Project Decision Information
Stove Draw Fence Relocation
Decision Signed Date: 10/13/2017
Forests:
Nez Perce-Clearwater National Forest
Districts:
Palouse Ranger District
States:
Idaho
Counties:
Latah
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Katlyn Howisey
1700 Highway 6
Potlatch, ID 83855
208-875-1740
katlynmhowisey@fs.fed.us
Last Updated: 10/18/2017