Smith Ridge
The Smith Ridge project would decrease insect and disease mortality and improve oveall forest health and ecological funtion.
Project Summary
Current Status:
Completed
Location Summary:
Ridgetop area spanning three watersheds between Minnesaka Creek (Little N. Fork of Clearwater River, Salmon Creek (N. Fork Clearwater River), and Isabella Creek, 40 air miles northeast of Orofino, ID.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/28/2018 |
| Decision | 12/2022 (Estimated) |
| Implementation | 07/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (25), 36 Cfr 220.6(E)(25)
Special Authority:
Hfra Title Vi: Insect And Disease Projects
Lead Management Unit:
North Fork Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products
Project Activity:
Forest Vegetation Improvements; Timber Sales (Green)
Project Decision Information
Smith Ridge Project
Decision Signed Date: 12/22/2022
Forests:
Nez Perce-Clearwater National Forest
Districts:
North Fork Ranger District
States:
Idaho
Counties:
Clearwater
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Andrew Skowlund
12730B Highway 12
Orofino, ID 83544
218-229-8830
andrew.skowlund@usda.gov
Last Updated: 12/22/2022