Swartz Meadow Beaver Dam Analogs
Construct Beaver Dam Analogs using hand tools along 1-mile stretch of the Pinnacle Creek headwaters to address incised channel, bank sloughing, and to capture sediment. Locations of BDAs to be determined under the direction of Forest Hydrologist.
Project Summary
Current Status:
Completed
Location Summary:
Township 28 North, Range 3 East, Section 8, Idaho County, Idaho.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/15/2018 |
| Decision | 04/2020 (Estimated) |
| Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Watershed Improvements
Project Decision Information
Swartz Meadow Beaver Dam Analogs
Decision Signed Date: 04/06/2020
Forests:
Nez Perce-Clearwater National Forest
Districts:
Salmon River Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Crystal Dannar
304 Slate Creek Road
White Bird, ID 83554
208-983-1950
cdannar@fs.fed.us
Last Updated: 9/16/2020