East Fork Relief Creek Fuels
Treat 68 acres (17 units) within 200 feet around private property through hand thinning, hand piling/burning and raising canopy base heights. The fuels treatments would be maintained over the long term.
Project Summary
Location Summary:
Township 28 North, Range 8 East Sections 16,17,20 and 21; Idaho County, Idaho
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/27/2020 |
Decision | 08/2024 (Estimated) |
Implementation | 08/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Cancelled
Forests:
Nez Perce-Clearwater National Forest
Districts:
Red River Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jennie Fischer
300 American River Road
Elk City, ID 83525
208-983-4048
jennie.fischer@usda.gov
Last Updated: 10/20/2024