Allison and Ericson Dams Removal
Remove or modify 11 existing dam embankments, and complete wetland and stream restoration within Allison Creek and Ericson Creek watersheds.
Project Summary
Current Status:
Completed
Location Summary:
Allison Creek watershed is located 8 miles west of Elk City, Idaho. Ericson Creek watershed is located 6 miles northwest of Elk City, Idaho.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/11/2024 |
| Decision | 12/2024 (Estimated) |
| Implementation | 04/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
Allison and Ericson Dams Removal
Decision Signed Date: 12/20/2024
Forests:
Nez Perce-Clearwater National Forest
Districts:
Red River Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robyn Smith
300 American River Road
Elk City, ID 83525
208-842-2140
robyn.smith@usda.gov
Last Updated: 12/20/2024