Fenn Face
The Nez Perce National Forest, Moose Creek Ranger District, proposes to use prescribed fire to treat approximately 3200 acres in the Johnson Creek, Rock Creek and Rackliff Creek drainages near the Fenn Ranger Station along the lower Selway River Corridor.
Project Summary
Current Status:
Completed
Location Summary:
Moose Creek Ranger District
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/21/2008 |
| Comment Period | 11/21/2008 |
| Decision | 12/2009 (Estimated) |
| Implementation | 06/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Moose Creek Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Fuels Management; Wildlife, Fish, Rare Plants
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Project Decision Information
Fenn Face Prescribed Fire Project
Decision Signed Date: 12/08/2009
Legal Notice Date: 12/17/2009
Forests:
Nez Perce-Clearwater National Forest
Districts:
Moose Creek Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
T32N R7E, Sections 13, 14, 23, 24 and 25 and T32N R 8E sections 19, 20, 29 and 30.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Michael Ward
831 Selway Road
Kooskia, ID 83539
208-926-8936
michaelward@fs.fed.us
Last Updated: 1/8/2010