Dixie Special Use Permit Reissuance (Ward)
The Red River Ranger District proposes to reissue a special use permit to Sibyl Ward for an existing 4 foot by 4 foot spring box and a one inch diameter 415 foot water transmission line which crosses National Forest system lands to her residence.
Project Summary
Location Summary:
National Forest system lands near the town of Dixie, Idaho
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/15/2012 |
Decision | 07/2012 (Estimated) |
Implementation | 09/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (10)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Red River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Cancelled
Forests:
Nez Perce-Clearwater National Forest
Districts:
Red River Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
T26N R8E Section 27
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public